07:19am- Concrete crew is now onsite! Staking of the corners was done yesterday in the pit. 08:18am- Rebar tying is going great so far this morning. Crew planning pour for 14:00 this afternoon. 09:35am- Top mat now tied and up rights are sorted out. 11:14am- While I went to pick up testing equipment for concrete; uprights are now getting placed! 11:55am- Pump truck is now onsite and concrete crew stated pour would start at 13:00 now. 13:05pm-pour begins and I have pulled cylinder’s and done tests. Air: 4.7%, Slump: 3” and Temperature: 68*F. 4 cylinders are made. Placement of concrete is going good. 14:07pm- Pour is completed! 14:25pm- No more work to be done here today. I will be headed off site.