Hwy 86 Sewer Ph 1
08:07am- Crew arrives now. They had to go pick up more forms before coming here. They will be working to get rest of LS formed up first. 09:32am- Rest of corner bars tied in LS and crew moving to west wall to finish rebar here. 11:00am- All rebar is now placed! Crew will finish tying all crossings. 13:12pm- Upper form work begins! 15:25pm- Gaining! 17:43pm- Not much left now! No straightening has occurred on top portion yet. 18:28pm- Crew is about to wind things down for the day. A huge jump in production today! 18:54pm- Crew is setting last panel now!