Hwy 86 Sewer Ph 1
07:19am- Concrete crew is now onsite! Staking of the corners was done yesterday in the pit.
08:18am- Rebar tying is going great so far this morning. Crew planning pour for 14:00 this afternoon.
09:35am- Top mat now tied and up rights are sorted out.
11:14am- While I went to pick up testing equipment for concrete; uprights are now getting placed!
11:55am- Pump truck is now onsite and concrete crew stated pour would start at 13:00 now.
13:05pm-pour begins and I have pulled cylinder’s and done tests. Air: 4.7%, Slump: 3” and Temperature: 68*F. 4 cylinders are made. Placement of concrete is going good.
14:07pm- Pour is completed!
14:25pm- No more work to be done here today. I will be headed off site.