Hwy 86 Sewer Ph 1
11:26am- Pit has been dug out and I’m told they have 1-2 more feet to remove. Excavator has been breaking all morning and has not left for anything.
12:10pm- Cleanup occurs at ARV area near STA 26+42.
14:03pm- 3/4 way complete with this layer of rock breaking now!
14:54pm- Bottom pit done with breaking now and top rock portion needs taken back a bit for upper wall forming.
16:17pm- Bucket is now on as clay is removed from top edge so bottom can be then cleaned out!
16:50pm- Operator picking up for the end of the day.
Should return tomorrow to continue digging broken rock out of pit area.