06:57am- Crew to begin gravity portion today at MH A-01 location. 09:31am- Crew has finally begun digging at MH A-02 at top of gravel road to begin laying pipe downstream today. 12:11pm- Base of MH A-02 is set, but laser wouldn’t go past -15% slope. Now digging from existing MH 02 in edge of road uphill to MH A-02 at a grade of 15.97%. 13:06pm- Crew is now laying pipe with everything in line now. 14:45pm- 112’ of gravity line now in place! 15:52pm- A look from the top down. 17:44pm- Cree now calling it a day. 16’ left to go to MH A-02.