Hwy 86 Sewer Ph1

Image
Contractor started at 9:45am assembling newly acquired spools started to set valve assembly in vault. GRE employee did not have access to blogger, but took many pictures. Alignment of pipe so they can install a link seal Contractor continue with lining up valves in valve vault. Installing last link seal Contractor is done for the day

Hwy 86 Sewer Ph 1

Image
8:15am Contractor setting lid on top of wet well 10:00am Contractor started to place pump rails 12:14pm Contractor is going to set valve vault. 12:34pm Valve vault set, making minor adjustments 2:45pm Contractor placed concrete flooring in valve vault 3:07 pm Contractor to finish concrete floor and head home will return on Wednesday morning Drain pipe from Valve Vault in place with check valve installed. Flow meter set in place

Hwy 86 Sewer Ph 1

Image
7:45am Contractor attempting to position valve vault box 8:43am Contractor starting to assemble parts inside wet well 9:40am Installing pipes inside wet well  10:02am Contractor continue to install pipes 10:45pm Contractor will finish tightening bolts and call it a day until Monday

Hey 86 Sewer Ph 1

Image
9:10am Contractor still drilling holes into wet well 10:40am Setting valves and pipes in vault  1:10pm Contractor received a new drill bit. Continue to drill wet well. Flat creek has opted to leave construction site and return tomorrow morning after holes in wet well have been completed 2:46pm Sub-Contractor completed holes in wet well. Will return tomorrow to install valve vault.

Hwy 86 Sewer Ph 1

Image
12:06pm Contractor drilling hole for future pipe to be placed through Arena lift station wet well.   1:34pm First hole complete  2:08pm Contractor starting on hole #2 2:54pm contractor to finish drilling holes and will call it a day. 3:00pm Flat creek crew left to locate parts for tomorrow