Hwy 86 Sewer Ph 1


07:09am- Working today due to snow that occurred this past Monday- Grade is checked first thing and we are at subgrade in pit! Rest of the rock to be removed and site should get prepped for ingress of materials!

07:44am- Dug out and grades are good!

09:20am- After airing up tire on haul truck, crew will load material from dig back yesterday and then start moving rock to roadway. 

10:20am- Clay is now moved out of the way so rock can be applied. 

11:23am- Rock is now making way to the top for roadway. 

12.28pm- Loads of rock are getting spread now and “beat” into road bed. 

13:29pm- Roadbed subgrade is now established to culvert area as hammerhead is getting soil removed from this area for rock. 



Ramp into holding tank area is also established. 

14:51pm- Rock now going in for hammerhead turn around. 

15:27pm- This concludes the work here today. Final grading of  tank location to occur next week. 