07:07am- Picked up cylinders feom pour yesterday and checked temperature of concrete since it was not covered yesterday. Current temperature on site by truck is 29*F.
In Forsyth today to do smoke test. 14:36pm- Rock is still being broke out today on the continuing section. The section north of the roadway that was built by Big Cedar now has 240’ of line laid today. Rock has been breaking rock along this section over the last few days. I will be headed back offsite this afternoon to take smoke testing equipment back to Springfield storage.
07:08am- Crew is back to locate electrical supply this morning and see what clearance we will have if any… 07:38am- Water line for fire station is found, electric for island sign and still looking for main power crossing. 08:38am- North end of bore now exposed. Survey to shoot flow line today on each end. 09:46am- Thrust block is poured at STA 60+25 approximately. Ditch is getting dug back to end of pipe from utilities located earlier. 10:44am- 1st joint now tying back into line for the day headed towards fire hydrant location. 11:24am- 60’ of pipe now in. 11:56am- 80’ now placed with gravel and ditch tape. 12:46pm- 100’ of pipe is now in. Backfill will continue. 14:06pm- Backfill completed! 14:09pm- Two more joints to be added to bore. 14:34pm- A total of 140’ is now loaded into casing! 15:23pm- Spoils have been moved to allow traffic from middle of drive. 15:30pm- Sweeping is now also completed across asphalt areas! Crew is c...
7:04 AM contractors plans for the day set lid on valve vault, grout vault box and water, flow meter box backfill with soil, install ladder into valve vault. The first set of stainless steel, intermediate rail supports were incorrect after they sent out a second set we noticed that they were welded too close together contractor cut them apart and re-welded Set lid on valve vault Compaction completed for the day Contractor finished for the day might possibly show up Thursday or Friday of this week
Comments
Post a Comment