Hwy 86 Sewer Ph 1
06:20am- Crew to begin this morning running forcemain on back towards AWWOB. 06:59am- Excavating side of slope to begin digging! 09:40am- 22.4*bend will be installed here for final turn to tank. 10:27am- Crew is now stopping here with thrust block poured on fitting too ensure proper elevation once valve box is set in place in oder to achieve the high point required for ARV. 10:41am- Cleanup and such will continue today to get things along line route tidied up! No more work here to be done until LS site changes take place and we are still waiting on valve vault and lids for AWWOB.