Hwy 86 Sewer ph 1
07:16am- Crew will continue pipe work today from near STA 20+00.
09:21am- Awaiting concrete fir six slope anchors that have been installed so far.
11:07am- 7 slope anchors are now in place!
15:35pm- More slope anchors created this afternoon for another six to be poured tomorrow.
16:34pm- 320’ of pipe is laid today. The additional six slope anchors will be poured tomorrow. No more pipe will be placed today.