Hwy 86 Sewer Ph 1


07:50am- Crew started at 6:00am today and will rest of this week to make up for the short day on Thursday due to the concert. 
80’ of pipe laid this morning!

Nearing crest of hill at STA 24+00 with one more slope anchor to build after this one shown here. 

09:10am- STA 24+80 is location of area for plug valve. 

12:42pm- 360’ now placed today so far!

13:22pm- Concrete begins on last 10 slope anchors. 



13:46pm- This is 8th one and more concrete will be nee to finish out. 



14:58pm- Last 2 slope anchors get concrete now!



15:12pm- Done with slope anchors now. 

15:22pm- 460’ of pipe now placed so far as we are now at STA 27+75 approximately. I will be headed offsite to Hwy 165 job for some approvals today. 










Comments

Popular posts from this blog

Hwy 86 Sewer Ph 1

Hwy 86 Sewer Ph 1

Hwy 86 Sewer Ph 1