Hwy 86 Sewer Ph 1
06:05am- Rebar cage will be finshed being buit first thing this morning and then concrete will be placed today.
07:33am- Cage is built and now we are awaiting concrete.
08:03am- Concrete begins.
08:51am- Rebar is now covered.
08:55am- A top coat will now be done to use up rest of the concrete that has been ordered.
I will be headed offsite for a bit to check HEY 165 job.
10:15am- Crew is calling it a day since they are at a good stopping point and with the need to be off site by noon anyways due to the concert tonight.