Hwy 86 Sewer Ph 1


07:25am- Crew will be crossing new roadway to begin burning again to get things cleaned up. ARV to go in and digging up of main line to install slope anchors that were missed at STA 28+50. 

07:58am- We have fires again!

ARV at STA 15+17 going in. 

08:36am- Worked stopped at ARV as they are awaiting a drill bit. Casting is placed on plug valve adjacent to Jones Rd. 

09:07am- Starting now to install missed slope anchors beginning at STA 28+60 ish. 

09:49am- 1st on is now dug out and it will be right at STA 27+50 due to bell location. 

10:50am- Rebar is now almost finished set for the four slope anchors!

12:38pm- Concrete begins on these four slope anchors!

12:46pm- Last one!

13:58pm- Last 3’ diameter lid goes on structure in ph 1. 

14:15pm- A look at the AWWOB. Based on scum line, it appears the last concert went ok. 

14:36pm- Valve for ARV’s at STA 30+94 & 25+30. 

15:00pm- I will be heading offsite for rest of the day. Crew to be moving some materials back towards AWWOB to begin work there tomorrow. 