Hwy 86 Sewer Ph 1
Crew will be working today to finish up clearing and benching along force main adjacent to power lines. Stakes will meed to be moved for this to happen and I will be onsite to ensure of their placement back to where originally staked. 07:56am- Dozer begins pushing bank off to bench for lune work. 08:35am- Crew attempts to take shot on existing staking, but are unable to work the unit properly. Staking will need ti be redone now at this point here. 09:43am- Well, so far he has been able to work around the stakes and has left them in place here! 13:48pm- Dozer back at it! Equipment broke down and had to be fixed- 14:13pm- Area going in behind pond is now getting leveled up! 15:23pm- Making small creek crossing more passable. 15:54pm- Cutting ground now to try and start leveling this section! Line runs near timber line. 16:39pm- Dozer has quit running… Hopefully its a fuel issue due to the angle of its tank… 17:18pm- Skidsteer with portable tank will be ...