Hwy 86 Sewer Ph 1

Image
Crew will be working today to finish up clearing and benching along force main adjacent to power lines. Stakes will meed to be moved for this to happen and I will be onsite to ensure of their placement back to where originally staked.  07:56am- Dozer begins pushing bank off to bench for lune work.  08:35am- Crew attempts to take shot on existing staking, but are unable to work the unit properly.  Staking will need ti be redone now at this point here.  09:43am- Well, so far he has been able to work around the stakes and has left them in place here! 13:48pm- Dozer back at it! Equipment broke down and had to be fixed- 14:13pm- Area going in behind pond is now getting leveled up! 15:23pm- Making small creek crossing more passable.  15:54pm- Cutting ground now to try and start leveling this section! Line runs near timber line.  16:39pm- Dozer has quit running… Hopefully its a fuel issue due to the angle of its tank… 17:18pm- Skidsteer with portable tank will be ...

Hwy 86 Sewer Ph 1

Image
Crew not working this morning due to it being to wet. 

Hwy 86 Sewer Ph 1

Image
06:57am- Light rain currently as crews are onsite waiting to see if they can work today.  08:30am- Crew has decided not to work to lay pipe today due to the rains. More clearing will take place up power line area. 

Hwy 86 Sewer Ph 1

Image
Contractor not sure if they are working today… Say they are still waiting on pipe to show up.

Hwy 86 Sewer Ph 1

Image
Apparently no work here today… I have drove and looked at the staking for the forcemain and took pictures. Spoke with John Escobar this morning and he hopes to have a plan in place by end of day. Edge of parking lot towards power lines.  Coming out from AWWOB crossing under power lines to west side.  Looking SW from power lines. Area behind pond.  Looking from coming out from behind pond towards the upper area towards new well.  Steep area that will need to be benched! From benching area towards steep uphill climb! Better view of steep climb.  From top of steep climb, looking back down towards pond area.  On top looking on towards next hump at well site.   At well area where line turns to go back under power lines back to the east.  Area to be cleared along slope to get around well site.  Looking up towards 86 LS site.  From 86 LS site looking back towards well site. 

Hwy 86 Sewer Ph 1

Image
No work today. Staking to occur on west line for forcemain and pipe to show up today!

Hwy 86 Sewer Ph 1

Image
No crews working around AWWOB today!

Hwy 86 Sewer Ph 1

Image
06:46am- Crew working to get water pumped out of AWWOB so the bottom hole can get cored into wet well.  08:07am- Water is pumped out! Awaiting Coring company to show up now.  08:50am- Well, work here for today is now stopped- No hole to be cored and crew not working on site today now.  I will be headed offsite. 

Hwy 86 Sewer Ph 1

Image
08:11am- Grass seed and straw is laid out along Fire Station 4 after ditch line was recut to drain properly.  08:18am- Delay with starting here today due to some emergency that Nabholz had and needed FlatCreek  first thing this morning.  08:42am- Excavator begins digging for source of water this morning! 08:57am- Water disappeared! No more evidence of it… 09:10am- Excavator has dug back about as far as it meeds to now. Cleanup along main roadway on east side will begin.  10:50am- Lifts of material going back in now! 11:07am- More fill to replace whats been taken out! 12:16pm- Lift continues along east side of basin.  13:23pm- Another angle! 14:30pm- Nearing top. I have reminded them of the fact that base rock has to go down, so don't get it to high! 15:52pm- Foundation drain is extended on north side! Fill on east side is done now until gravel is placed.  16:48pm- Crew calling it a day!

Hwy 86 Sewer Ph 1

Image
07:25am- Crew is getting equipment back to site this morning. Rest of the seali g of walls was completed last Friday! 08:21am- Having dozer cut out this area due to fatty material.  08:58am- After cutting grade to rid the fatty wet material, water shows up…this is probably the reason for it. This will drain to the west now instead of down the road path.  09:54am- Coring begins today for inlets and overflow.  10:31am- More gravel being placed against walls.  11:50am- Coring of overflow 12” hole is now underway.  12:44pm- I had to stop coring process, just in the nick of time as he was preparing to core hole 13” to high off of sump area.  Contractor crew not paying any attention to whats going on; all just assuming it’s good! 13:39pm- More dirt continues to be hauled in on south slope.  14:48pm- Bring lift on around to east side now.  15:05pm- Having more cut out where water seems to be sitting at.  15:41pm- More gravel being placed at wall as ...