Hwy 86 Sewer Ph 1
Crew will be working today to finish up clearing and benching along force main adjacent to power lines. Stakes will meed to be moved for this to happen and I will be onsite to ensure of their placement back to where originally staked.
07:56am- Dozer begins pushing bank off to bench for lune work.
08:35am- Crew attempts to take shot on existing staking, but are unable to work the unit properly.
Staking will need ti be redone now at this point here.
09:43am- Well, so far he has been able to work around the stakes and has left them in place here!
13:48pm- Dozer back at it! Equipment broke down and had to be fixed-
14:13pm- Area going in behind pond is now getting leveled up!
15:23pm- Making small creek crossing more passable.
15:54pm- Cutting ground now to try and start leveling this section! Line runs near timber line.
16:39pm- Dozer has quit running… Hopefully its a fuel issue due to the angle of its tank…
17:18pm- Skidsteer with portable tank will be going up to put more fuel in dozer. I will be beaded off site for today.