In Forsyth today to do smoke test. 14:36pm- Rock is still being broke out today on the continuing section. The section north of the roadway that was built by Big Cedar now has 240’ of line laid today. Rock has been breaking rock along this section over the last few days. I will be headed back offsite this afternoon to take smoke testing equipment back to Springfield storage.
23:45pm- Sign will be removed first thing tonight for road crossing work. 00:09am- Light plant is now up and running! 02:16am- Roadway is now almost cut and transit is aligned to MH A-03 from MH A-02. 03:37am- 1st joint placed finally! Heading across Devils Pool Rd now. 05:41am- Halfway across road. Clean fill gravel going in now to switch over traffic. 06:47am- Directing of traffic going well. 07:28am- Another look at traffic. 08:38am- Both lanes now passable as we are into fire station area now. 09:20am- 112’ of pipe laid this morning. Crew will continue with backfill gravel to get further away from roadway.
06:57am- Crew to begin gravity portion today at MH A-01 location. 09:31am- Crew has finally begun digging at MH A-02 at top of gravel road to begin laying pipe downstream today. 12:11pm- Base of MH A-02 is set, but laser wouldn’t go past -15% slope. Now digging from existing MH 02 in edge of road uphill to MH A-02 at a grade of 15.97%. 13:06pm- Crew is now laying pipe with everything in line now. 14:45pm- 112’ of gravity line now in place! 15:52pm- A look from the top down. 17:44pm- Cree now calling it a day. 16’ left to go to MH A-02.
Comments
Post a Comment