Hwy 86 Sewer Ph 1
08:11am- Grass seed and straw is laid out along Fire Station 4 after ditch line was recut to drain properly.
08:18am- Delay with starting here today due to some emergency that Nabholz had and needed FlatCreek first thing this morning.
08:42am- Excavator begins digging for source of water this morning!
08:57am- Water disappeared! No more evidence of it…
09:10am- Excavator has dug back about as far as it meeds to now. Cleanup along main roadway on east side will begin.
10:50am- Lifts of material going back in now!
11:07am- More fill to replace whats been taken out!
12:16pm- Lift continues along east side of basin.
13:23pm- Another angle!
14:30pm- Nearing top. I have reminded them of the fact that base rock has to go down, so don't get it to high!
15:52pm- Foundation drain is extended on north side!
Fill on east side is done now until gravel is placed.
16:48pm- Crew calling it a day!