Hwy 86 Sewer Ph 1


08:11am- Grass seed and straw is laid out along Fire Station 4 after ditch line was recut to drain properly. 

08:18am- Delay with starting here today due to some emergency that Nabholz had and needed FlatCreek  first thing this morning. 

08:42am- Excavator begins digging for source of water this morning!

08:57am- Water disappeared! No more evidence of it…

09:10am- Excavator has dug back about as far as it meeds to now. Cleanup along main roadway on east side will begin. 

10:50am- Lifts of material going back in now!

11:07am- More fill to replace whats been taken out!

12:16pm- Lift continues along east side of basin. 

13:23pm- Another angle!

14:30pm- Nearing top. I have reminded them of the fact that base rock has to go down, so don't get it to high!

15:52pm- Foundation drain is extended on north side!

Fill on east side is done now until gravel is placed. 

16:48pm- Crew calling it a day!