07:25am- Crew is getting equipment back to site this morning. Rest of the seali g of walls was completed last Friday!

08:21am- Having dozer cut out this area due to fatty material. 

08:58am- After cutting grade to rid the fatty wet material, water shows up…this is probably the reason for it. This will drain to the west now instead of down the road path. 

09:54am- Coring begins today for inlets and overflow. 

10:31am- More gravel being placed against walls. 
11:50am- Coring of overflow 12” hole is now underway. 

12:44pm- I had to stop coring process, just in the nick of time as he was preparing to core hole 13” to high off of sump area. 
Contractor crew not paying any attention to whats going on; all just assuming it’s good!
13:39pm- More dirt continues to be hauled in on south slope. 

14:48pm- Bring lift on around to east side now. 

15:05pm- Having more cut out where water seems to be sitting at. 

15:41pm- More gravel being placed at wall as water continues to bleed from ground here!

15:59pm- Plywood covers cored hole for gravity line now!

16:41pm- This will be all of the fill placed today! Roller will now compact it!

16:50pm- Area now compacted!