Hwy 86 Sewer Ph 1
23:45pm- Sign will be removed first thing tonight for road crossing work. 00:09am- Light plant is now up and running! 02:16am- Roadway is now almost cut and transit is aligned to MH A-03 from MH A-02. 03:37am- 1st joint placed finally! Heading across Devils Pool Rd now. 05:41am- Halfway across road. Clean fill gravel going in now to switch over traffic. 06:47am- Directing of traffic going well. 07:28am- Another look at traffic. 08:38am- Both lanes now passable as we are into fire station area now. 09:20am- 112’ of pipe laid this morning. Crew will continue with backfill gravel to get further away from roadway.