Hey 86 Sewer Ph 1

















07:59am- Crew is digging under power and other utilities this morning to get force main a bit closer to bore. This is mostly hand digging. 
























09:39am- Slow process this morning…
























11:21am- Still digging under utilities…
























12:45pm- Pipes now going in. 
























13:33pm- Making sure of positive grade. This is the last joint to be placed here today. 60’ total. 
























13:48pm- Area for tie now dug out! Crew will finish the day marking out and cutting path through fire station concrete. 




















14:30pm to 16:15pm - Meeting at new LS site at Arena. 

17:16pm- Clearing for MH A2 and down to LS occurring. This will round out the day. 