Hwy 86 Sewer Ph 1
07:46am- Crew has switched jobs this morning. They are currently getting road ready for asphalt patching off Jones Rd.

09:22am- Crew back doing rebar for slope anchors…
10:02pm- Slope anchors in now awaiting concrete.

12:55pm- Concrete going in now.
14:55pm- Pipe now connected to MH A-02.
Line is also lamped by laser.
-Had issue on 86 Hwy Job I had to go address…
16:45pm- Ditch over line coming up hill is almost filled up now on Tower Rd.
17:28pm- Work was going to continue tonight to do the road crossing, but excavator has gone down.