Hwy 86 Sewer Ph 1


06:57am- Crew to begin gravity portion today at MH A-01 location. 


















09:31am- Crew has finally begun digging at MH A-02 at top of gravel road to begin laying pipe downstream today. 


















12:11pm- Base of MH A-02 is set, but laser wouldn’t go past -15% slope. 
























Now digging from existing MH 02 in edge of road uphill to MH A-02 at a grade of 15.97%. 
























13:06pm- Crew is now laying pipe with everything in line now. 










































14:45pm- 112’ of gravity line now in place!










































15:52pm- A look from the top down. 
























17:44pm- Cree now calling it a day. 16’ left to go to MH A-02. 