Hwy 86 Sewer Ph 1


07:08am- Crew is back to locate electrical supply this morning and see what clearance we will have if any…


















07:38am- Water line for fire station is found, electric for island sign and still looking for main power crossing. 










































08:38am- North end of bore now exposed. Survey to shoot flow line today on each end. 


















09:46am- Thrust block is poured at STA 60+25 approximately. 
























Ditch is getting dug back to end of pipe from utilities located earlier. 
























10:44am- 1st joint now tying back into line for the day headed towards fire hydrant location. 
























11:24am- 60’ of pipe now in. 
























11:56am- 80’ now placed with gravel and ditch tape. 
























12:46pm- 100’ of pipe is now in. Backfill will continue. 
























14:06pm- Backfill completed!


















14:09pm- Two more joints to be added to bore. 
























14:34pm- A total of 140’ is now loaded into casing!
























15:23pm- Spoils have been moved to allow traffic from middle of drive. 



















15:30pm- Sweeping is now also completed across asphalt areas!


















Crew is calling it a day for the long weekend!