Hwy 86 Sewer Ph 1
07:08am- Crew is back to locate electrical supply this morning and see what clearance we will have if any…
07:38am- Water line for fire station is found, electric for island sign and still looking for main power crossing.
08:38am- North end of bore now exposed. Survey to shoot flow line today on each end.
09:46am- Thrust block is poured at STA 60+25 approximately.
Ditch is getting dug back to end of pipe from utilities located earlier.
10:44am- 1st joint now tying back into line for the day headed towards fire hydrant location.
11:24am- 60’ of pipe now in.
11:56am- 80’ now placed with gravel and ditch tape.
12:46pm- 100’ of pipe is now in. Backfill will continue.
14:06pm- Backfill completed!
14:09pm- Two more joints to be added to bore.
14:34pm- A total of 140’ is now loaded into casing!
15:23pm- Spoils have been moved to allow traffic from middle of drive.
15:30pm- Sweeping is now also completed across asphalt areas!
Crew is calling it a day for the long weekend!