Hwy 86 Sewer Ph 1


Crew arrived onsite at 07:35am. Plan today is to continue tying rebar horizontal bars and possibly start putting up forms. 

08:56am- Steel going up!

10:19am- Slow progress…

12:33pm- A load of 6’ forms are getting set off at this time. 

14:41pm- rebar tying still going strong!

16:41pm- Crew gathered around pit area to get rest of corner bars placed. This will round out the day. 