Hwy 86 Sewer Ph 1


07:02am- Wall crew to be onsite today to begin tying horizontal steel in walls. 
No one onsite at this time. 

07:40am- Crew now onsite and starting with getting rebar verticals level. 

10:04am- Extending uprights and getting marks laid out for squaring walls. 

13:22pm- Been trying to figure out why things didn’t look right. Spoke with Jacob and wall height is from grout edge, not from floor…so we are raising vertical bars 2’ to make elevation grade of 1135.50! Yes, we shot bench mark and then top of bars allowing for 3” coverages. It is now correct height. 

15:12pm- Horizontal bar tying now occurring on East wall while more upright tying continues. 

16:45pm- Thunder and rain starting! Crew is packed up and headed out for the day!