Hwy 86 Sewer Ph 1


Crew will begin setting forms today! Corner bars are completed now in place!
07:55am- Crew onsite at 7:25am. Forms and bracing to begin. 


I will now be headed offsite to Judicial Center for a concrete pour this morning. 

11:15am- Back onsite with forms starting to stand in south east corner. 

13:18pm- Forms still going up!

14:12pm- Gaining; slowly!
15:51pm- 2/3 of the forms are up now with bracing poles being added. 

17:25pm- Crew is now gone and David Kribs (KEI) was here to discuss working 12 hour days. I told him to run it past John Escobar so he can take it up the ladder!