Hwy 86 Sewer Ph 1

Image
07:14am- Crwws will ne working today to begin digging here at Arena LS site and to finsh setting ARV’s.  07:39am- D26 ARV now set at STA 45+81.  08:00am- Structure at STA 26+42 to be set along with ARV.  08:34am- Structure now placed.  08:59am- Gravel being placed now around pipe.  09:13am- D26 ARV now set.  09:29am- Work at Arena LS site. A couple more trees had to come out on the lower SW corner.  09:48am- Water going in force main now at STA 62+00.  10:37am- Gravel going in over exposed utilities.  11:59am- Cleanup work around fire hydrant area here ar Branson Cedars is underway! 12:53pm- D25 ARV installed at STA 41+32.  13:55pm- Defining edge so large rocks can be placed back in a row again. Water continues to be pumped into the force main as well! 14:08pm- Gravel will now be placed around lateral line going to the back corner of the fire station.  14:23pm- Lateral line now graveled! 15:36pm- Force Main is now full of water! It ...

Hwy 86 Sewer Ph 1

Image
Contractor not working today- to wet he says!

Hwy 86 Sewer Ph 1

Image
Spoke with contractor this morning and its to wet to work at Arena site, so ARV work on Ph 1 will continue today.  09:32am- Have been dealing with getting the right ARV’s to the right locations with crew. Model D25 and 26’s are both utilized on this project! 09:56am- Crew is now back to STA 3+56 to install ARV and set structure.  11:13am- Structure and ARV now placed! 12:05pm- Crew calling it a day!💁🏼

HWY 86 Sewer Ph 1

-No work today due to rain.

Hwy 86 Sewer Ph 1

Image
07:19am- Excavator making way back down to stock the fire. More work to continue on LS site here after staking occurs this morning.  08:35am- Lime Green flagged stakes are the corners of the basin. White are offsets.   Fire now being stoked! 9:48am-Plan now is to get road built back to where trucks can get in for future work at collection box.  10:57am- Toad is coming along nicely!  13:34pm- Haul truck has flat now so road building will stop. Excavator stokes the fire one last time for today, and crew will call it a day. 

Hwy 86 Sewer Ph 1

Image
14:09pm- I was offsite this morning for a meeting in Appleton City. Crew is currently digging to get lateral line connected main and ran back a bit so rest of ditch can be backfilled here.  14:24pm- Area LS site getting cleared today! 15:33pm- I arranged a meeting with Marty (Big Cedar) and John (Flatcreek) to go over what needs to happen here at this site for now with tree removal. Trees from this point on will only be taken out on an as needed basis with approval first.  Test holes to be dug today and mud to be pushed to toe of parking lot to build mound.  16:28pm- Excavator now moving mud to slope. Dozer wasn’t able to push it any further.  16:46pm- Lateral connection is now ran to back corner of fire station. More gravel to be placed tomorrow as cleanup will take rest of the day. 

Hwy 86 Sewer Ph 1

Image
07:17am- crew has declared this morning to cold to work…will resume next week. 

Hwy 86 Sewer Ph 1

Image
07:17am- Crew is back today to begin again. Water will be introduced into the east end of force main at MH A-04 location.  08:41am- Main is now ready for water, but well is froze up now so this will be delayed… 09:08am- MH A-03 now has replaced Con-Shield top. 10:01am- Line passes mandrel test from A-02 to A-03. 10:23am- Line pass air test from MH A-03 to A-02.  10:59am- Line passes mandrel test from MH A-02 to MH 02(existing).  11:35am- Line passes air test from MH A-02 to MH 02(existing).  12:15pm- A vacuum test was started on MH A-02, but I reminded them of the grade rings that need to be placed first.  13:12pm- Crew prepares to pull mandrel through bore from A-03 to A-04.  13:19pm- Mandrel has now been pulled from MH A-04 to A -03.  13:46pm- Line passes air test between MH A-04 & A-03.  14:28pm- MH A-03 Having issues not passing vacuum test… 15:27pm- MH A03 now passing vacuum test! 16:41pm- After picking up all testing gear from today crew...