Hwy 86 Sewer Ph 1

07:17am- Crew is back today to begin again. Water will be introduced into the east end of force main at MH A-04 location. 

























08:41am- Main is now ready for water, but well is froze up now so this will be delayed…
09:08am- MH A-03 now has replaced Con-Shield top.
10:01am- Line passes mandrel test from A-02 to A-03.
























10:23am- Line pass air test from MH A-03 to A-02. 
10:59am- Line passes mandrel test from MH A-02 to MH 02(existing). 



















11:35am- Line passes air test from MH A-02 to MH 02(existing). 
12:15pm- A vacuum test was started on MH A-02, but I reminded them of the grade rings that need to be placed first. 

13:12pm- Crew prepares to pull mandrel through bore from A-03 to A-04. 
13:19pm- Mandrel has now been pulled from MH A-04 to A -03. 
13:46pm- Line passes air test between MH A-04 & A-03. 
14:28pm- MH A-03 Having issues not passing vacuum test…
15:27pm- MH A03 now passing vacuum test!

16:41pm- After picking up all testing gear from today crew will be delivering structures to the ARV locations on the project and should be here tomorrow to begin setting them.


















16:56pm- Crew still can not get water from hydrant! They will put off filling line now until next week. 












Comments

Popular posts from this blog

Hwy 86 Sewer Ph 1

Hwy 86 Sewer Ph 1

Hwy 86 Sewer Ph 1