Hwy 86 Sewer Ph 1
14:09pm- I was offsite this morning for a meeting in Appleton City. Crew is currently digging to get lateral line connected main and ran back a bit so rest of ditch can be backfilled here.
14:24pm- Area LS site getting cleared today!
15:33pm- I arranged a meeting with Marty (Big Cedar)
and John (Flatcreek) to go over what needs to happen here at this site for now with tree removal. Trees from this point on will only be taken out on an as needed basis with approval first.
Test holes to be dug today and mud to be pushed to toe of parking lot to build mound.
16:28pm- Excavator now moving mud to slope. Dozer wasn’t able to push it any further.
16:46pm- Lateral connection is now ran to back corner of fire station. More gravel to be placed tomorrow as cleanup will take rest of the day.