07:07am- Back to digging on gravity line here at fire station. Plan is to get line to MH A-03 and set it; then get bore tied into it. 08:06am- Having the curb cut due to damage so it can be torn out and redone when pad is repaired. 10:32am- Curbing is now removed and ditch is to manhole location. Excavator now digging to get bore ditch over to manhole location. 11:40am- Ditches are almost together! One more truck load to be taken out should do it! 12:27pm- Ditches are now together and manhole to be set next! 13:27pm- MH A-03 set now and line is lamped by laser to MH A-02. 14:52pm- Crew sets 27” con-shield barrel section onto MH A-02. After ram-neck, cone goes on. 15:17pm- Cone placed onto MH A-03 base now. 16:34pm-MH A-03 is now blocked off and gravel has been placed around it to a point. MH A-02 is now graveled up as well. Dirt is getting pulled up from edges on Tower Road and into middle of roadway so that the dozer can fix the road back...