Hey 86 Sewer Ph 1
07:28am- Crew has now moved pipe up to bore location and are installing the last few sections of pipe with the spacers that arrived finally.
07:59am- 1st of 3 joints with spacers going in this morning.
09:21am- 3.5 joints in now to complete loading of the bore! This last skid will be loosened and moved up into the bore pipe.
09:55am- Back over to the north side of bore now laying gravel for more pipe.
10:39am- Line is now tied into MH A-03 and service connection wye is installed for fire department future connection.
Line is lamped by light back through bore from MH A-03.
11:04am- Boot is now around casing and pipe on north end. Gravel backfill to continue.
12:43pm- Crew mow at existing MH 02 thats been cored to make pipe connection.
13:14pm- Line is now connected to MH 02.
90* turn down will fit!
13:21pm- Gravel backfill now going in as pipe gets chinked in place.
13:53pm- Work is now starting to get lateral laid for fire department so that when the main line is tested, it will be as well! LP line and service lateral are both located.
15:14pm- Digging on lateral run has stopped and crew is now working to set MH A-04 on south end of bore.
15:51pm- Base is set, pipe connected and boot seal now going on casing and pipe.
16:24pm- gravel is now placed around pipe and backfill begins.
16:51pm- Crew has buttoned up the hole and is calling it a day.