Hwy 86 Sewer Ph 1
07:07am- Back to digging on gravity line here at fire station. Plan is to get line to MH A-03 and set it; then get bore tied into it.
08:06am- Having the curb cut due to damage so it can be torn out and redone when pad is repaired.
10:32am- Curbing is now removed and ditch is to manhole location. Excavator now digging to get bore ditch over to manhole location.
11:40am- Ditches are almost together! One more truck load to be taken out should do it!
12:27pm- Ditches are now together and manhole to be set next!
13:27pm- MH A-03 set now and line is lamped by laser to MH A-02.
14:52pm- Crew sets 27” con-shield barrel section onto MH A-02.
After ram-neck, cone goes on.
15:17pm- Cone placed onto MH A-03 base now.
MH A-02 is now graveled up as well. Dirt is getting pulled up from edges on Tower Road and into middle of roadway so that the dozer can fix the road back.
17:04pm- Parking area for fire department is now swept! Crew is winding down for the day.