Hwy 86 Sewer Ph 1
06:53am- Under rainy skies, crew continues to dig through parking lot today here at Branson Cedars.
07:47am- 1st joint of the day is now in place.
08:46am- 3rd joint getting gravel now.
08:57am- Burning taking place also today since rain is falling!
09:36am- 5th joint going in!
10:40am- Joint #6!
12:05pm- Joint #7 getting gravel now.
13:20pm- 8th joint laid. 160’ now in place!
14:06pm- LS site adjacent to Hwy 86 is cleared now with burn pile started!
14:11pm- LS site at Arena area is getting cleared now!
14:19pm- Area from Jones Spur to a point across from Dollar General has been hydro seeded.
14:38pm- 9.5 joints now in with a 11.25* bend going in at approximately STA 60+25.
16:15pm- 210’ now placed!
17:16pm- Open ditch is barricaded and final cleanup is underway- 210’ today installed.