06:53am- Under rainy skies, crew continues to dig through parking lot today here at Branson Cedars. 


















07:47am- 1st joint of the day is now in place. 
















































08:46am- 3rd joint getting gravel now. 
























08:57am- Burning taking place also today since rain is falling!


















09:36am- 5th joint going in!
























10:40am- Joint #6!
























12:05pm- Joint #7 getting gravel now. 
























13:20pm- 8th joint laid. 160’ now in place!
























14:06pm- LS site adjacent to Hwy 86 is cleared now with burn pile started!


















14:11pm- LS site at Arena area is getting cleared now!



















14:19pm- Area from Jones Spur to a point across from Dollar General has been hydro seeded. 



















14:38pm- 9.5 joints now in with a 11.25* bend going in at approximately STA 60+25. 
















































16:15pm-  210’ now placed!
























17:16pm- Open ditch is barricaded and final cleanup is underway- 210’ today installed. 