Hwy 86 Sewer Ph 1



7:04 AM contractors plans for the day set lid on valve vault, grout vault box and water, flow meter box backfill with soil, install ladder into valve vault. The first set of stainless steel, intermediate rail supports were incorrect after they sent out a second set we noticed that they were welded too close together contractor cut them apart and re-welded



Set lid on valve vault

Compaction completed for the day






Contractor finished for the day might possibly show up Thursday or Friday of this week