Hwy 86 Sewer Ph 1
07:29am- Casing for Jones Rd is now being welded together.

09:09am- Last section getting welded before its lowered into ditch.
09:09am- Last section getting welded before its lowered into ditch.
10:30am- Casing is being lowered into ditch here at Jones Rd crossing after initial bedding of ditch.
Gravel getting placed over casing now!
11:01am- Crew moved to Casing location under Thunder Ridge Rd.
12:14pm- Digging is now underway here at Thunder Ridge Rd.
14:21pm- Getting close to having ditch dug for casing…
16:24pm- Ditch is dug and crew begins welding casing for this crossing.
17:38pm- Crew is calling it a day. More welding to resume in the morning.