07:23am- Crew preparing to add more pipe to casing this morning here at Jones Rd. 

07:52am- Last piece of pipe going into casing!

09:17am- 45* bend getting installed at STA 20+83 approximately. 

10:24am- Section of pipe being placed into 45* fitting. 
11:46am- north east end of casing tied in now to main line. 

Fitting is wrapped!

12:46pm- Pipe is getting gravel now to get caught back up with backfilling. 

13:32pm- Boots are now getting installed on casing and pipe. 

Ditch tape is being ran across roadway!

13:52pm- Both ends now finished with boots and fittings wrapped. 

14:56pm- 22.5* bend is installed at STA 20+21 approximately. 

15:52pm- Pipe is in now to STA 19+50. Gravel and backfill to follow. 

17:21pm- Pipe is now laid out to STA 18+84. Crew is calling it a day. Approximately 300’ of pipe laid today. 