Hwy 86 Sewer Ph1
Contractor is excavating soil to install the air release/vacuum valve vault
Flow meter valve installed
Finish connecting for main lines
2:34pm air valve vault set
2:47pm flow meter tight, stands adjusted and torqued
3:30pm contractor tried installing stainless steel, intermediate rail, supports, and they were the wrong size, so remove them back out and started filling up ditch where force main comes out of wet well
5:30pm contractor filled in soil around volts won’t be back until Monday, depending on weather