Hwy 86 sewer Ph 1


9:20am contractor on site preparing to set flowmeter vault. Plan for the day is to plumb the meter inside the vault and connect the force main to the existing force main previously installed.





10:00am lifting chains to set flowmeter vault have arrived. Crew preparing to set vault on site two crew one foreman one excavator.







11:48am crew has finished setting flowmeter vault and has piping connected to valve vault. Excavator is down, concrete for floor of flow meter vault to be here by 1 PM. Crew planning to also work tomorrow for pipe connection to existing force Maine. Concrete arrived a little after 1 PM and was extremely wet rejected truck and asked for another batch. Second truck rejected because of wet concrete waiting for a third to arrive.


3:40pm Set second half of box on valve vault




Poured concrete floor for flow meter vault