Hwy 86 Sewer Ph 1
A look at the rip rap placed yesterday at STA 10+60.
07:45am- Crew will proceed to lay pipe from STA 18+00 today going up steep hill. Slope anchors will begin near STA 18+25.
I will be heading offsite for a concrete pour at the overlook at 9am.

11:17am- 200’ of pipe is laid with slope anchors set at every other joint currently.

12:39pm- Pipe laid for today will be 240’ and six slope anchors built. Crew will round out the day with moving materials on up the hill to the top today and string out pipe. No more pipe to be placed today.
11:17am- 200’ of pipe is laid with slope anchors set at every other joint currently.
12:39pm- Pipe laid for today will be 240’ and six slope anchors built. Crew will round out the day with moving materials on up the hill to the top today and string out pipe. No more pipe to be placed today.