Hwy 86 Sewer Ph 1
08:50am- Crew has placed 60’ of pipe so far today. Late start for me due to having to drop off truck for brake service today.
10:11am- A bot more rock breaking needs to occur to get under creek properly.
11:28am- 140’ of pipe now placed. Rock was removed for proper alignment.
13:22pm- Pipe is now through creek cut and rebar cage is being built around it!
14:37pm- Awaiting concrete arrival now!
16:14pm- concrete and casement will round out the day. I will be headed offsite to pick up my work truck.