Hwy 86 Sewer Ph 1
07:25am- Crew awaits concrete arrival for encasement at STA 10+60 area.
08:22am- Re-staging of material to near STA 18+00 occurring while we still await concrete for encasement.
08:41am- Pouring of thrust block occurs first!
08:54am- Encasement occurs now.
09:07am- Done!
10:35am- Clean up along the creek channel occurs and rocks will outline new channel over center of encasement once completed.
11:27am- Materials have been moved to near STA 18+00.
Pipe work will be picking back up here near STA 15+60 area.
11:49pm- Just marked a couple more trees fir removal to be burned with the rest of the others for clean up purposes. These were on the edge of the rock ditch from pictures taken on the 29th of May. Crew said no problem and would take care of them.
12:36pm- Establishing a high point in pipe for ARV location.
12:40pm- High point now established! New location @STA 15+17 approximately.
14:03pm- ARV structure will not fit over line. Dog house openings are off. It will need to be cut!
15:00pm- After multiple cuts and such, another block had to still be added to get dog houses over pipe…
16:21pm- 140’ of pipe installed today! Crew is picking up and moving more things to this side now.