Hwy 86 Sewer Ph 1
Crew breaking rock this morning and burning trees.
10:14am- Pipe laying continues today near STA 15+10 area. ARV location to change from plan location.
Rock breaking still occurring near STA 10+60 respectively.
12:15pm- Still breaking rock near STA 10+60.
Crew will be attempting to get this section tied in today between roadway and 10+60 area.
14:51pm- Ditch is now dug to get both sections of pipe tied together here near STA 10+60.
15:26pm- pipes are now tied together and 45*fitting wrapped.
16:58pm- Cage is now built for pipe! Crew is calling it a day as rains begin.