Hwy 86 Sewer Ph 1


Contracted to continue with breaking rock and building the cage for encasement to get across power easement. 
I will not be on site until possibly noon due to a pre-con meeting in Springfield. 
06:57am- Dennis just sent this picture to me! They will be working on getting all the cave ins from the heavy rain last night shoveled out !

11:49am- Crew now has all debris removed from around the pipe and from cage! Concrete is on its way!

12:31pm- Concreting begins!

13:02pm- nearing half way of pipe laid. 

14:24pm- 75’ of encasement now completed!

15:11pm- Crew prepares to set a 45*fitting at STA 5+19 approximately. 

16:32pm- Another 45* bend is set at STA 5+22 approximately. 

Rock will be broken out rest of the day!