Hwy 86 Sewer Ph 1
Contracted to continue with breaking rock and building the cage for encasement to get across power easement.
I will not be on site until possibly noon due to a pre-con meeting in Springfield.
06:57am- Dennis just sent this picture to me! They will be working on getting all the cave ins from the heavy rain last night shoveled out !
11:49am- Crew now has all debris removed from around the pipe and from cage! Concrete is on its way!
12:31pm- Concreting begins!
13:02pm- nearing half way of pipe laid.
14:24pm- 75’ of encasement now completed!
15:11pm- Crew prepares to set a 45*fitting at STA 5+19 approximately.
16:32pm- Another 45* bend is set at STA 5+22 approximately.
Rock will be broken out rest of the day!