Hwy 86 Sewer Ph 1
07:19am- Another picture of floor in the AWWOB after it has dried out some.
07:24am- Rock breaking occurring this morning as we near the power line easement.
08:29am- 1st joint for today getting gravel!
08:55am- 2nd joint going in!
10:07am- Another joint goes in and the encasement will statt from this point.
12:00pm- 100’ now placed as cage begins around pipe within easement of power lines.
13:18pm- Cage is coming along as is the rock breaking!
13:41pm- Another joint placed and cage will continue!
16:14pm- Crew now has rebar tied and ready now for next joint now!
16:55pm- Crew has laid 160’ of pipe and built a cage for 60’ of it in the power line easement. This will conclude the day here.