Hwy 86 Sewer Ph 1
07:31am- Water is being pumped from manhole so that coring can take place this morning sometime.
08:22am- AWWOB is now getting pumped out so that I can document the cracks in the grout.
10:53am- Crew has now started the forcemain at STA 3+00 approximately.
11:41am- 40’ of pipe now placed!
12:08pm- Entered AWEOB to begin taking pictures.
13:04pm- Backfill is underway now that ditch tape is placed! Crew left site here to go to top area to work at the Arena for about an hour I was told.
15:43pm- 80’ of pipe now placed along with 45* fitting set at approximate STA 3+42.
15:59pm- Concrete going in now for thrust block at STA 3+42.
16:29pm- Backfill will round out the day with 80’ laid today!