Hwy 86 Sewer Ph 1


07:31am- Water is being pumped from manhole so that coring can take place this morning sometime. 

08:22am- AWWOB is now getting pumped out so that I can document the cracks in the grout. 

10:53am- Crew has now started the forcemain at STA 3+00 approximately. 

11:41am- 40’ of pipe now placed!

12:08pm- Entered AWEOB to begin taking pictures. 











13:04pm- Backfill is underway now that ditch tape is placed! Crew left site here to go to top area to work at the Arena for about an hour I was told. 

15:43pm- 80’ of pipe now placed along with 45* fitting set at approximate STA 3+42. 

15:59pm- Concrete going in now for thrust block at STA 3+42. 

16:29pm- Backfill will round out the day with 80’ laid today!