Hwy 86 Sewer Ph 1
07:56am- Ditch work continues today! Only excavator working here currently. Rest of crew is at Arena-
09:30am- Crew is getting ready to take a shot for ensuring that we do not create a false high spot as we come from behind pond area!
10:02am- Gravel going in ditch now behind pond to get pipe laid on up to excavator.
12.09am- 60’ of pipe now placed in ditch with 45* bend set and wrapped! More gravel to follow!
13:03pm- Thrust block on 45 needs more concrete and was relayed to the contractor! Gravel will continue to be placed over pipe.
13:44pm- Additional concrete has now been placed at 45* bend!
Also, approximately 80’ of pipe has now been placed and bedded.
16:46pm- Crew has laid 140’ of pipe now and rock is being dug from trench where hammer has broken out too! This will conclude posts for today!