Hwy 86 Sewer Ph 1


07:56am- Ditch work continues today! Only excavator working here currently. Rest of crew is at Arena-

09:30am- Crew is getting ready to take a shot for ensuring that we do not create a false high spot as we come from behind pond area!

10:02am- Gravel going in ditch now behind pond to get pipe laid on up to excavator. 

12.09am- 60’ of pipe now placed in ditch with 45* bend set and wrapped! More gravel to follow!

13:03pm- Thrust block on 45 needs more concrete and was relayed to the contractor! Gravel will continue to be placed over pipe. 

13:44pm- Additional concrete has now been placed at 45* bend!

Also, approximately 80’ of pipe has now been placed and bedded. 

16:46pm- Crew has laid 140’ of pipe now and rock is being dug from trench where hammer has broken out too! This will conclude posts for today!