Hwy 86 Sewer Ph 1
06:49am- AWWOB is pumped down this morning!
Crew has a slow start this morning as the hammer is getting attention again this morning!
08:47am- Just got done with showing TCRSD crew the AWWOB and discussed layout and such of all main installed all the way back to the fire station and Tower road.
FlatCreek crew back breaking rock now!
09:38am- Digging out, but more breaking rock to come!
11:16am- 1 joint of pipe placed so far today! Possibly one more before noon at which they will call it a day due to concert! No contractor is allowed to work past Noon today…
11:52am- Crew calls it a day with 40’ of pipe laid for today! 2 joints!