Hwy 86 Sewer Ph 1


07:28am- Well, Crew is going to work today to lay pipe on forcemain, but first, a quick look at the AWWOB!

07:53am- Cage for pipe crossing power line easement is getting extended the rest of the way this morning. Concrete to arrive around noon today. 

Pipe to be laid to get past 45*bends so thrust blocks can be poured at the same time as the encasement. 

09:07am- Concrete arrives early and encasement continues. 

45* bends also get concrete. 

11:46am- Hammer is getting repairs at this moment!

12:08pm- Back to rock breaking!

15:20pm- 90’ of pipe now laid as more rock will need broke out. 

16:26pm- Rock breaking will round out the day here!