Hwy 86 Sewer Ph 1
07:06am- Just barely sprinkling here. Dozer is getting worked on and should be back running shortly.
07:36am- Back cutting slope to bench in flat spot for future digging of line.
08:34am- John Escobar shows up this morning to get a better understanding of whats going on with the project!
10:00am- Burning begins today as the benching is gaining ground.
11:19am- Looking back south from top!
12:37pm- Larger dozer now, D6 since we have this steep grade to deal with on getting it leveled up.
More diesel going on fire to help it along!
13:29pm- Excavator dragging large tree to burn pile!
Alignment stake now gone!
14:23pm- Excavator was swapped out for another and tree is fi ally getting put on fire!
15:20pm- Excavator now on top moving more trees and brush!
16:07pm- Trackhoe is broke down!
16:34pm- Gravel and pipe are now staged under the power lines…
16:50pm- I will now be heading offsite!