Hwy 86 Sewer Ph 1
Awaiting cylinder breaks this morning so that we can see if backfill can begin on AWWOB.
08:05am-
Cylinder Breaks AWWOB walls- 7 day-
Set 1: 2,980
Set 2: 2,887
Set 3: 3,138
08:45am- Had a Teams meeting with Jacob and Spencer on breaks. They are ok with only going up halfway with gravel and backfill until we reach the 80% of 4000psi.
Met with John Escobar onsite and went over next steps for backfill. He needs to put in 6” drain pipe around perimeter per note 23 pg.24 of plan set.
He will gather materials and move equipment back down to begin work, but wont be until after lunch.
14:54pm- 6” pipe is going in in footer and gravel to follow to hold pipe in place.
15:43pm- 2” clean rock going in to cover pipe and hold it in place.
16:40pm- Dirt going in along gravel as compactor makes passes.
16:58pm- Crew calling it a day!